Reply To: Argh! My coal mine won't produce

Home Forums General Discussion Argh! My coal mine won't produce Reply To: Argh! My coal mine won't produce

#17908
isidoro
Participant

Apart from the items pointed out before, consider that frequency isn’t the only quantity to check.  Imagine a frequency of 6 min., but with 6 vehicles in the line.  In that case, the piece of goods has to wait an average of 3 min. for a vehicle to arrive plus (6 by 6/2 = 36/2)  18 min, travel time.  That makes 21 min => that line won’t be chosen…